The Ranch of Questionable Choices

Complete Build Guide — The Main Run

Quictent 18×9 ft galvanized run on leveled block foundation
Model: CC001 · SKU: 13301P · Central Texas bedrock site

Contents

  1. Before You Start — Terms, Tools, and Materials
  2. Project 1: The Main Run
    1. Materials List
    2. Phase 1 — Site Layout & String Lines
    3. Phase 2 — Block Walls & Foundation
    4. Phase 3 — Deck Pedestals & 4×4 Sill Beams
    5. Phase 4 — Ground Cloth, Grid & Sand
    6. Phase 5 — Quictent Frame Assembly
    7. Phase 6 — Aviary Netting & Predator Apron
    8. Phase 7 — Interior Setup
    9. Phase 8 — Pre-Launch Checks
  3. Quictent 18×9 ft Assembly Guide
    1. Parts Inventory
    2. Steps 1–12: Frame Through Final Securing
    3. TROQC Post-Assembly Checklist
    4. Warranty Reference

Before You Start

A Note for First-Time Builders

This guide assumes you have never built anything before. Every term is explained when it first appears. Every step tells you not just what to do but why — so if something doesn't look right while you're building, you'll understand the goal well enough to fix it yourself.

Read each step fully before you start doing it. Surprises mid-step are how mistakes happen.

Lumber Sizes — The Confusing Truth

Important: Lumber names are NOT their actual measurements. A "2×4" is actually 1.5 inches wide by 3.5 inches tall. A "4×4" is actually 3.5 inches by 3.5 inches. A "1×4" is actually 0.75 inches by 3.5 inches. These names are just what they're called at the hardware store. All measurements in this guide use the actual real-world dimensions.

Glossary of Terms

TermWhat it means
Bottom plateThe horizontal board that sits on the ground/foundation. The vertical boards (uprights) attach to it.
Top plateThe horizontal board that runs along the top of the wall. Uprights attach to this too.
Upright / studA vertical board between the bottom plate and top plate. These form the "walls."
ToenailingDriving a screw at an angle through the side of one board into another. Used when you can't screw straight through the face.
On center (OC)"24 inches on center" means the distance from the middle of one upright to the middle of the next is 24 inches.
PlumbPerfectly vertical — straight up and down.
LevelPerfectly horizontal — flat, not tilted.
SquareTwo pieces meeting at exactly 90 degrees (a right angle).
Hardware clothA rigid wire mesh — like a very stiff window screen but made of thicker wire. Used for predator-proof enclosures.
Hog ring clipsSmall metal rings crimped shut with pliers to join two pieces of hardware cloth together.
Predator apronHardware cloth laid flat on the ground outside the run walls. Stops predators from digging under the wall.
Knee braceA diagonal board at a corner that prevents the structure from racking (leaning sideways).
SpliceJoining two boards end-to-end to make a longer run.

Tools You Will Need

Measuring & Marking

Cutting

Fastening

Other


Project 1: The Main Run

The Quictent 19.7×9.8×6.6 ft galvanized run, built on a leveled foundation of concrete blocks, 4×4 sill beams, and deck pedestals, sitting on a sloped bedrock site. Four-sided perimeter block wall contains the sand base. Aviary netting roof. Extended predator apron on all sides.

Full Materials List — Project 1

ItemQtyNotes
Quictent 19.7×9.8×6.6 ft kit (extended apron version)1Galvanized poles, hardware cloth sides, predator apron included
8×8×16" concrete blocks40Main wall blocks — 20 original + 20 extra
6×8×16" concrete blocks6Transition zone on short end walls
4×8×16" concrete blocks6Stepping shims on short end walls
2×8×16" concrete blocks4Uphill long side — spot footings only
4×4 × 8 ft lumber3Corner uprights and splice support post for breezeway (not used in main run)
4×4 × 10 ft lumber6Sill beams — run along the top of the block walls
Adjustable deck pedestals (1-3/16" to 2-3/8" range)246 per 4×4 beam × 4 beams — sit between blocks and beams
Ground cloth / landscape fabric1 rollCovers the interior floor before gravel grid
Gravel stabilization gridTo fitGoes on top of cloth, under sand
Sand (already delivered)3 tonsDone
2" aviary nettingTo cover roofFrom prior project — soft catch for flushing birds
Zip ties (heavy duty)100+Securing netting to frame ribs
Flat pavers~20Weighting the predator apron on bedrock surface
Masonry anchors + drill bit1 packFor anchoring sill beams to bedrock where possible
3" exterior screwsBox of 100General fastening
Phase 1 — Site Layout & String Lines

Before a single block goes down, you need reference lines on the ground showing exactly where everything will go. This is the most important phase. Every measurement after this comes from these lines.

1
Drive your metal form stakes at the four corners

Find a crack in the bedrock at each of the four planned corners of the run. Drive a metal form stake into each crack. If the bedrock is solid with no cracks, wedge the stake against a rock edge or weight it with a heavy block — it just needs to hold tension on the string.

Stakes go outside the corner — 6 to 12 inches beyond where the wall will be. The string represents the outside face of your wall. You need room to work between the stake and the actual block.

Why outside: if the stakes were inside the perimeter, the string would be in the way of placing the blocks. You'd have to lift the string every time.
run interior 19.7 ft × 9.8 ft stake stake stake stake string line (outside face of wall) greenhouse side uphill

Top-down view: stakes (orange dots) go outside the corner. String (dashed) shows outside face of wall.

2
Pull string lines between stakes at the correct height

Tie string between the stakes. This string represents the top of your block wall — the level plane everything is built to. Use your level on the string: pull it tight and adjust until the bubble is centered. This is your most important reference — everything else is measured from it.

The slope is 9 inches over 10 feet. The string on the uphill side will be lower to the ground (about 2 inches above grade) and the string on the downhill side will be higher above the ground (about 9+ inches above grade). That's correct — the string stays level while the ground slopes.
3
Check that your rectangle is square (the 3-4-5 method)

A rectangle that looks square might not be. To check: measure 3 feet along one string from a corner stake. Mark it. Measure 4 feet along the adjacent string from the same corner. Mark it. The diagonal between those two marks should be exactly 5 feet. If it is, the corner is square. Check all four corners.

If a corner is off, move one stake slightly until the diagonal measures exactly 5 feet.

A run that isn't square means the Quictent frame won't sit properly, the gates won't latch, and the whole structure will fight you from the start. Fix it now when it costs nothing.
3 ft 4 ft should = 5 ft corner stake ↑ check here

3-4-5 check: measure 3 ft and 4 ft from the corner along each string. The diagonal must be exactly 5 ft.

Phase 2 — Block Walls & Foundation

Your run sits on a sloped bedrock site. The concrete blocks serve two purposes: they level the structure, and they form a three-sided wall that contains the sand. The uphill long side needs only spot footings because that side is nearly flush with grade.

Understanding the slope and how blocks compensate for it

bedrock level plane — top of all blocks 8×8×16 on end 6×8×16 4×8×16 pedestal 2×8×16 4×4 sill beam (level) 9" downhill (low) uphill (high)

Foundation cross-section: blocks get shorter as you go uphill because the ground rises to meet the level plane.

4
Lay the downhill long wall first (the tall wall)

This is your most important wall — it contains the most sand and sets the reference for the short end walls. Use 8×8×16 blocks placed on end (8" face pointing up). Run them continuously for 19.7 feet (about 15 blocks).

As you place each block, hold your level on top. The string line above tells you how high the top of the block should be — the top of the block should just touch or nearly touch the string. Adjust by placing the block on a thin shim of sand if needed.

Starting with the downhill wall anchors your reference. Both short end walls will butt against it at the corners.
5
Lay the short end walls, stepping across the slope

Each short end wall runs 9.8 feet across the slope. The ground rises 9 inches from one end to the other, so the blocks get progressively shorter as you move uphill. Here's the block order from downhill corner to uphill corner:

Butt the short end walls against the ends of the downhill long wall — no overlap at the corners needed.

level plane (top of all blocks) 8×8×16 on end 8×8×16 flat 6×8×16 6×8×16 4×8×16 4×8×16 pedestal gap — back with h/w cloth downhill corner uphill corner

Short end wall: blocks step down from tallest (downhill, left) to nearly nothing (uphill, right). Dashed blocks are 4×8×16 shims.

6
Pin hardware cloth to the inside face of the short end walls before adding sand

The stepping creates gaps between the bottom of the upper blocks and the bedrock below them (the ground has dropped away). Sand will pour through these gaps unless you close them.

Cut strips of hardware cloth about 8 inches wide. Press them against the inside face of each short end wall from the top of the blocks down to the bedrock. Staple or wire-tie to the blocks. The sand you pour in later will press the cloth flat against the wall and hold it in place.

Do this before sand goes in. It's impossible to do after.
block gap hardware cloth sand presses cloth flat cloth extends to bedrock

Hardware cloth (green line) pressed against the inside wall face closes the gap between block bottom and bedrock. Sand pressure holds it.

7
Lay the uphill long wall (continuous, low profile)

The uphill long side is nearly flush with the grade — only about 2 inches of rise needed across the full 19.7 feet. Use 8×8×16 blocks laid flat (4" face up) for this wall. They don't need to be tall — they just need to close the perimeter and give the 4×4 sill beam a resting surface. The pedestal handles the fine adjustment.

8
Set the four uphill spot footings

The uphill long side gets 4 individual spot footings (not a continuous wall). Place one 2×8×16 block flat on the bedrock at each pedestal position. Space them evenly across the 19.7 ft length — approximately every 5 feet. These blocks barely poke above grade — their only job is to give the pedestal a flat seat on the uneven bedrock.

Phase 3 — Deck Pedestals & 4×4 Sill Beams

The deck pedestals are the fine-leveling layer between the blocks and the 4×4 sill beams. They adjust from 1-3/16" to 2-3/8", which means as long as your blocks get you within about 2 inches of the level plane, the pedestal closes the gap.

9
Set all 24 deck pedestals on top of the blocks

Place one pedestal on top of each block position. You have 4 sill beams, 6 pedestals per beam. Twist the pedestal to adjust its height before placing the beam — it's much easier to dial them in now than to shim after the beam is down. Set each pedestal to approximately the right height using your string line as a guide.

Tip: The pedestal has a threaded collar you twist to raise or lower it. Clockwise raises, counter-clockwise lowers (or vice versa — check your specific model). A couple of turns makes a big difference — go slowly.
concrete block deck pedestal twist to adjust 1-3/16" to 2-3/8" 4×4 sill beam (level) check level here

Pedestal detail: sits on block, 4×4 beam rests on top. Twist the pedestal collar to raise or lower before setting the beam.

10
Lay the 4×4 sill beams

You have 6 beams at 10 feet each. Two beams run along each of the two long sides (the 19.7 ft sides). To cover 19.7 feet with 10-foot beams you need to splice them end-to-end.

Critical splice rule: The joint where two beams meet must land directly on top of a pedestal — never between pedestals in mid-air. Plan your pedestal positions so one of them falls at exactly 10 feet (120") from the end of the first beam. Then lay the first beam (10 ft) and butt the second beam against it on top of that same pedestal.

Offset the splice location between the two parallel beams on the same side — don't let both joints land at the same pedestal.

beam 1 (10 ft) beam 2 (rest of run) splice joint pedestal block ✓ correct — joint lands on pedestal ✗ wrong — joint in mid-air

Splice joint must land on a pedestal (good, left example). Never in mid-air between pedestals (wrong, right example).

11
Check level across all four corners and diagonally

Place your level on each sill beam and check it's level along its length. Then place the level across the two parallel long beams at several points to check they're level side-to-side. Finally, measure the two diagonals of the rectangle — corner to corner in both directions. They must be equal. If they're not, the rectangle is twisted and the Quictent won't sit flat.

This is your last easy correction point. Once the Quictent frame is on, fixing a twisted foundation means taking the whole thing apart. Spend 10 minutes here.
Phase 4 — Ground Cloth, Grid & Sand
12
Lay ground cloth inside the perimeter

Roll the landscape fabric inside the block perimeter, covering the entire bedrock floor. Tuck the edges up against the inside face of the block walls — like tucking a fitted sheet. This cloth prevents weeds from growing up through the sand and keeps the sand layer from migrating into the rock cracks.

13
Lay the gravel stabilization grid on top of the cloth

Unroll or unfold the grid on top of the cloth, cutting to fit at the edges. The grid's honeycomb cells hold the sand in place under load so it doesn't shift or rut when the birds walk on it. The cloth, grid, and sand work together as a three-layer floor system.

14
Distribute sand evenly

Spread the sand across the grid in an even layer. The 4×4 sill beams and block walls contain it. The sand should sit below the top of the sill beams — not mounding over them. Rake level.

bedrock ground cloth gravel stabilization grid sand wall wall 4×4 sill contains the sand edge ← layer 3 ← layer 2 ← layer 1

Floor layers from bottom to top: bedrock → ground cloth (layer 1) → gravel grid (layer 2) → sand (layer 3). Block walls and 4×4 sills contain the edges.

Phase 5 — Quictent Frame Assembly
15
Read the Quictent instructions first — then modify the plan

The Quictent assembles with button-style pole connections — you'll hear a click when they seat. Follow their sequence with one important change: leave the greenhouse-facing wall panel uninstalled. That wall will be replaced by the breezeway tunnel (Project 2). It's far easier to leave it out now than to cut it out after the frame is assembled.

Identify which wall faces the greenhouse before you start and set those panels aside.

16
Assemble the frame on top of the 4×4 sill beams

The Quictent base rail sits on top of the 4×4 sill beams. Assemble the frame with at least one other person — the poles are light but unwieldy alone. Start with the four corner uprights, then connect the base rail, then work upward.

Once assembled, secure the base rail to the 4×4 sills with screws or brackets. Central Texas wind will move an unsecured frame.

Phase 6 — Aviary Netting & Predator Apron
17
Attach aviary netting to the peaked roof — secured to every rib

Drape the 2-inch aviary netting over the peaked roof. Starting at the ridge, zip-tie the netting to every single pole rib — not just the outer edges. Use a zip tie every 12 inches along each rib. Pull the netting snug before each zip tie so there are no sag points.

A sagging roof net is a bird trap. A peafowl that panics at night will flush straight up. If the net has a sag, the bird's head goes through and it can't get back out.

Check every square foot for sag before the birds use the run. Run your hand across the whole roof from the inside.
zip ties every 12" along every rib (orange dots) netting drapes over peaked roof

Zip ties (orange dots) at regular intervals along every pole rib. No skipping ribs, no loose spans.

18
Install the predator apron — three walled sides

The Quictent kit includes an extended predator apron. Lay it outward from the base of the three block walls, flat on the ground, extending at least 18 inches beyond the wall. On bedrock you cannot bury it, so weight it instead: lay flat pavers or spare concrete blocks on top of the apron along the outer edge. A predator will try to dig at the base of the wall, hit the apron, and give up rather than walk out 18 inches and dig there.

19
Install hardware cloth skirt on the uphill side — surface pinned

The uphill side has spot footings, not a continuous wall, so the kit's apron is the primary defense here. Lay hardware cloth flat outward from the frame base, extending 18 inches. Weight the outer edge with pavers. This is the bedrock method — no burying, just weighting.

20
Add partial solid cover over one roof quadrant

Aviary netting alone provides no shade or rain protection. Add a tarp, polycarbonate panel, or solid cover over one quadrant of the roof — the quadrant that will be in afternoon shade if possible. Attach with zip ties or clips. This gives the birds a weather break on 95° June afternoons.

Phase 7 — Interior Setup
21
Install a low perch or natural log at 18–24 inches height

Peafowl will stand on anything elevated. Give them a sanctioned option or they'll pick something less ideal. A natural log or a 4×4 offcut on two short post supports works well. No need for anything fancy — they just need something to step up onto.

22
Position water and feed in separate corners

Place the water station and feed station at opposite corners of the run — not adjacent. Peafowl will stand in both containers simultaneously if you give them the opportunity. Separate corners also means less cross-contamination between feed and water.

23
Mount at least one camera with clear interior sightline

Position a camera where you can see most of the interior from the app. During nesting season and any time a bird seems off, you want to check without having to go out. Run power or confirm battery life before the run goes live.

24
Reinforce the main gate latch

The Quictent kit latch works for chickens. Add a secondary carabiner or a slide bolt above or below the primary latch. Morpheus has studied the primary latch. She will find out about the secondary one too, but it will buy time.

Phase 8 — Pre-Launch Checks
25
Walk the full perimeter at bird height

Get down to knee height and walk the entire perimeter slowly. Look for any gap larger than 1 inch between the hardware cloth and the block wall, or where the apron doesn't sit flush. Raccoon paws fit through 1×1 inch mesh. Pay special attention to the short end walls where the hardware cloth steps down — make sure it's pressed flat against the block faces with no daylight showing.

26
Do a nighttime walk with a flashlight before first use

Walk the outside of the run in the dark with a flashlight. You are looking for what a raccoon sees at night: low gaps, loose apron corners, any cloth not sitting flush. Anything that lets light through from inside is a gap worth fixing.

27
Introduce birds during daytime with breezeway open first

Let the birds discover the run on their own terms. Open the breezeway on the first day and let them walk through at their own pace. Don't herd them in. Morpheus especially — she will enter when she decides to, not when you decide for her.

Forcing birds into a new space the first time creates a negative association. Let it be their choice and they'll use it willingly.


Quictent 18×9 ft Run Assembly Guide

Customized for The Ranch of Questionable Choices. Model: CC001 · SKU: 13301P · Manual reference: Pages 12–21 (18×9 ft section only).

Site conditions: Leveled foundation of concrete blocks and 4×4 sill beams on bedrock. No ground stakes — using pavers/blocks to weight the base instead. Left long wall connects to greenhouse — middle ~3 ft section stays open for breezeway.

Before you start: This run ships in 2 cartons. Open both and confirm all components are present before you begin. Lay them out by part number on a tarp or clean surface so you can find them quickly.

Orientation — Know Your Walls

Stand outside the run footprint, facing where the door will be. That's the front.

Keep this orientation in your head for the entire build. Every time this guide says "left wall" or "greenhouse side," it means that 18 ft wall.

Parts Inventory — Poles

Part #DescriptionQtyWhat it looks like
#1Long Front Pole2Long pole with button connectors on ends
#2Side Pole 19Medium pole — horizontal side rails
#3Short Inner Door Pole (2 holes)1Short pole with 2 drilled holes
#4Back Pole 11Has a small nub/flag on one end
#5Roof Pole8Angled poles that form the peaked roof
#6Long Outer Door Pole (2 holes)1Longer door pole with 2 drilled holes
#7Door Top Cross Pole1Short horizontal pole across door top
#8Short Front Pole1Short front base pole
#9Long Outer Door Pole2Vertical door frame poles
#10Short Inner Door Pole1Vertical inner door pole
#11Inner Door Bend Pole1Has a bend for the door hinge area
#12Side Standing Pole9Vertical uprights along the walls
#13Bottom Bracing Pole12Short horizontal poles along the base
#14Back Pole 21Second back horizontal pole
#15Side Pole 24Mid-height horizontal side poles
#16Side Pole 32Additional side poles near corners
#17Top Bracing Pole4Horizontal poles inside the roof area
#18Back Standing Pole1Vertical upright on the back wall

Parts Inventory — Mesh & Covers

Part #DescriptionQty
Q1Hardware Cloth (welded wire mesh)1 roll
Q2Chicken Wire (hex mesh)1 roll
PRoof Cover (tarp)2

Parts Inventory — Hardware & Fasteners

Part #DescriptionQtyWhat it does
F4-Way Connector6Hub where 4 poles meet
G3-Way Connector6Hub where 3 poles meet
F3M6×35 Screws & Nuts2Pre-install at Poles 4/14 and 1/8
F4M6×60 Screws & Nuts (longer)9Secure key joints in the base frame
F5M6×20 Screws & Nuts (short)35General pole-to-pole fastening
LM8×50 Screws & Nuts (big)2Door hinge bolts
XScrew Cap46Plastic caps covering exposed screw ends
C1Pipe Clamp35U-shaped clamps that grip poles together
JDoor Switch (latch)2Latches to keep the door closed
OBungee Ball24Elastic balls holding roof cover to frame
NZip Tie750Attaching mesh to frame — you'll use a lot
WGround Stake24NOT USED — bedrock site, use pavers instead
MRiding Buckle12Strap buckles for top bracing poles
SGloves1 pairWear them — hardware cloth edges are sharp
T1Wrench M61For M6 bolts
T2Wrench M81For M8 bolts (door hinges only)
Ground Stakes (W): The manual assumes you're driving 24 stakes into dirt. You're on bedrock. Set all 24 stakes aside. Weight the base with pavers/blocks and secure the frame to your 4×4 sill beams with 3" exterior screws.
Quictent Step 1 — Pre-Install Two Screws (Don't Tighten Yet)

Manual reference: Page 16, Step 1

Parts needed: Pole #4 (Back Pole 1), Pole #14 (Back Pole 2), Pole #1 (Long Front Pole), Pole #8 (Short Front Pole), 1× F4 screw, 1× F3 screw

What you're doing and why

You're threading two screws into specific pole joints before you start building the frame. These joints will be hard to reach once the frame is standing. By pre-installing the screw (without the nut), you can quickly secure the joint later by just adding the nut.

How to do it

1
Pre-install F4 screw at Poles 4/14 joint

Find Pole #4 (Back Pole 1) and Pole #14 (Back Pole 2). Slide them together at their connection point. Thread one F4 screw (M6×60) through the hole at that joint. Do NOT attach the nut yet. Just leave the screw sitting in the hole so it's ready.

2
Pre-install F3 screw at Poles 1/8 joint

Find Pole #1 (Long Front Pole) and Pole #8 (Short Front Pole). Slide them together at their connection point. Thread one F3 screw (M6×35) through the hole at that joint. Do NOT attach the nut yet.

The F4 screw is longer than the F3 — don't swap them. F4 = 60mm, F3 = 35mm. "Pre-install" means the screw is in the hole but loose. You'll tighten these later.
Quictent Step 2 — Build the Base Rectangle and First End Walls

Manual reference: Page 16, Step 2

Parts needed: #1 ×2, #8 ×1, #15 ×4, #16 ×2, #12 ×8, #4 ×1, #14 ×1, F3 ×2, F4 ×9, G ×3, F ×3, #5 ×4, #2 ×2

What you're doing and why

This is the skeleton of the run. You're building the bottom rectangular frame (the footprint) and raising the first vertical uprights and a few roof poles on the two short end walls. Think of it as building two short-wall "A-frames" connected by the long base rails.

How to do it

1
Lay out the bottom perimeter on your sill beams

Two Pole #1 (Long Front Poles) form the two long sides of the base (18 ft each). Pole #8 (Short Front Pole) spans the front (9 ft, door side). Pole #4 + #14 (pre-assembled back poles from Step 1) span the back (9 ft).

2
Connect with G and F connectors

At each corner and mid-wall junction, use the 3-Way Connectors (G) and 4-Way Connectors (F) to join the poles. The connectors accept the pole ends — push until they click or seat fully.

3
Insert side standing poles and horizontal rails

Insert Side Standing Poles (#12) vertically into the connectors at the short end walls — these are the uprights that give the walls height. Add Side Pole 2 (#15) and Side Pole 3 (#16) as horizontal mid-height rails on the end walls to connect the uprights and stiffen them.

4
Attach roof poles for the peaked gables

Attach the first Roof Poles (#5) to form the peaked gable on the front and back walls. Each gable is two #5 poles meeting at a peak, with a 3-Way Connector (G) at the top.

5
Secure all joints with F4 screws

Secure all joints with F4 screws where the manual diagram shows them — these are the longer M6×60 bolts. Tighten the nuts on the pre-installed screws from Step 1 now.

Orientation matters. Before you tighten anything, confirm which long side faces the greenhouse. That's your left wall. Mark those two base poles with tape now.
Build on top of the sill beams. The base rail should sit directly on your 4×4s. Don't build on the ground and try to lift it — the 18 ft frame is unwieldy. Get a second person — the frame is light but floppy.
Quictent Step 3 — Build the Side Wall Frames (Both Long Walls)

Manual reference: Page 16, Step 3

Parts needed: G ×3, F ×4, #5 ×3 (or 4), #2 ×7

What you're doing and why

You're extending the structure along the two 18 ft long walls. This means adding the remaining Side Pole 1 (#2) horizontal rails and more Roof Poles (#5) along the length. The connectors (F and G) at each junction create the internal "ribs" of the structure — like ribs on a boat hull.

How to do it

Working along each long wall, insert Pole #2 (Side Pole 1) horizontally into the connectors — these are the horizontal rails at the top and mid-height. At each rib junction, install 4-Way Connectors (F) or 3-Way Connectors (G) depending on how many poles meet there. Add the remaining Roof Poles (#5) at each rib, forming the peaked gable shape all the way down the length. Push each pole fully into its connector until you feel or hear it seat.

Count your ribs. The 18×9 model has more internal ribs than the 12×9. Refer to the exploded diagram on page 13 — count the numbered circles along the long wall to make sure you're not skipping a rib position.
Greenhouse-side note: Build both long walls identically at this stage. The breezeway opening only affects the mesh later (Steps 8–10), not the frame itself. You want the full frame for structural strength.
Quictent Step 4 — Install the Door Assembly

Manual reference: Page 17, Step 4

Parts needed: #3 ×1, #6 ×1, #7 ×1, #9 ×2, #10 ×1, #11 ×1, J ×2, F5 ×2, C1 ×2, L ×2

What you're doing and why

You're building the door frame and hanging the door on the front (9 ft) wall. The door uses vertical poles (#9, #10, #3, #6), a horizontal cross pole (#7), a bend pole (#11) for the hinge mechanism, two large M8×50 bolts (L) as hinge pins, and two latches (J).

How to do it

1
Build the inner doorway frame

Locate the door opening on the front wall — the gap between two uprights in the center. Install Pole #10 (Short Inner Door Pole) and Pole #3 (Short Inner Door Pole with 2 holes) as the inner vertical frame. These attach to the base rail and the horizontal mid-rail. Install Pole #7 (Door Top Cross Pole) horizontally across the top of the door opening.

2
Build and hang the door

Build the door panel: Pole #9 ×2 (Long Outer Door Poles) are the vertical sides. Pole #6 (Long Outer Door Pole with 2 holes) connects between them. Pole #11 (Inner Door Bend Pole) creates the hinge attachment point.

Hang the assembled door onto the frame using the two L bolts (M8×50). These big bolts act as hinge pins — they go through the holes in the door poles and into the frame poles. Use the M8 wrench (T2) to tighten.

3
Attach latches and reinforce

Attach the two Door Switches (J) — one near the top, one near the bottom. Secure them with F5 screws (M6×20). Install 2× Pipe Clamps (C1) to reinforce the door frame connection.

The L bolts are your only M8 hardware. Everything else is M6. Use the M8 wrench (T2) for these two bolts only. Check door swing before tightening — it should swing freely without binding.
TROQC-specific: Reinforce the latch. The kit latches are designed for chickens. Add a secondary carabiner or slide bolt above or below the primary latch. Morpheus has already been observed studying latches. Do this before first bird introduction.
Quictent Step 5 — Install Bottom Bracing Poles and Remaining Uprights

Manual reference: Page 18, Step 5

Parts needed: #12 ×1, #18 ×1, F5 ×12, #13 ×25, C1 ×25

What you're doing and why

You're adding structural bracing to the bottom of the frame — the Bottom Bracing Poles (#13) run horizontally along the base between uprights all the way around the perimeter. They stiffen the base so it doesn't rack (shift into a parallelogram) and create attachment points for the hardware cloth. You're also adding the last vertical uprights (#12, #18).

How to do it

Install the remaining Side Standing Pole (#12) and Back Standing Pole (#18) at their marked positions. Lay the Bottom Bracing Poles (#13) horizontally along the base, connecting between each pair of uprights around the entire perimeter. Secure each bracing pole to the uprights with Pipe Clamps (C1) and F5 screws (M6×20). Tighten with the M6 wrench (T1).

How pipe clamps work: A pipe clamp is a U-shaped metal bracket. It wraps around one pole and bolts to another, locking them together at a perpendicular angle. The F5 screw passes through the clamp holes and into the pole. Tighten until snug — don't strip it.
This is tedious but critical. Every clamp you skip is a spot where the frame can flex and where mesh won't have an attachment point. Work your way around systematically — start at one corner and work clockwise.
TROQC site note: These bottom bracing poles sit right on top of your 4×4 sill beams. This is where you screw/bracket the Quictent base rails into the sill beams — use 3" exterior screws at every upright location. The manual doesn't tell you to do this because it assumes ground stakes, but on bedrock with sill beams, this is your primary hold-down.
Quictent Step 6 — Install Top Bracing Poles

Manual reference: Page 18, Step 6

Parts needed: #17 ×4, C1 ×8, F5 ×8, W ×24 (skip these), M ×12

What you're doing and why

The Top Bracing Poles (#17) run horizontally inside the roof area, beneath where the roof covers will sit. They prevent the peaked roof from spreading outward under wind load and support the roof cover from beneath so it doesn't sag and collect rainwater.

How to do it

Install the 4× Top Bracing Poles (#17) horizontally across the interior of the roof, connecting the two long walls at the top. They run perpendicular to the ridge line. Secure each end with Pipe Clamps (C1) and F5 screws. Install Riding Buckles (M) at the designated points.

Skip all 24 Ground Stakes (W). Set them aside.

What to do INSTEAD of ground stakes

Central Texas wind is no joke. If you're not anchoring to bedrock with masonry anchors, the frame-to-sill-beam screws plus the paver weight are your wind resistance. Don't skip either.
Positioning: The two roof covers (P) each span roughly half the roof length. Position the bracing poles to land beneath them. Make sure they're level — crooked poles pool water on the cover.
Quictent Step 7 — Ground-Level Preparation (Modified for Bedrock)

Manual reference: Page 19, Step 7

Parts needed: None from the kit — this uses your site materials

What the manual says vs. what YOU do

The manual shows staking the frame to the ground. On dirt, that means driving 24 ground stakes through the base frame into the soil. You're on bedrock. Here's what you do instead:

1
Confirm the frame sits squarely on all four sill beams

Walk the perimeter and check that the base rail contacts the 4×4 all the way around. Shim any gaps with thin plywood or composite shims.

2
Screw the base frame to the sill beams

At every upright location and at least every 3 feet in between. Use 3" exterior screws. Pre-drill to avoid splitting the 4×4.

3
Check diagonals

Measure the two diagonals (corner to corner, both directions). They should be equal. If they're off by more than an inch, loosen some screws and rack the frame gently until the diagonals match, then re-tighten.

4
Check stability

Push firmly on one corner at shoulder height. The frame should resist without significant flex. If it sways, add diagonal bracing with scrap lumber or a few temporary zip-tied poles.

This is your last easy correction point. Once the mesh goes on, fixing the frame geometry means cutting zip ties, pulling mesh, and starting over. Spend 15 minutes making sure everything is square and solid now.
Wind loading on bedrock is different. On dirt, stakes resist uplift. On bedrock with sill beams, your resistance comes from the weight of the blocks, the beam-to-block connection, and the frame-to-beam screws. Make sure every connection in that chain is solid.
Quictent Step 8 — Measure and Cut the Hardware Cloth

Manual reference: Page 19, Step 8

Parts needed: Q1 (Hardware Cloth roll), zip ties from N, wire cutters (not included — bring your own)

What you're doing and why

The Hardware Cloth (Q1) is the welded wire mesh that forms the lower walls of the run — this is your predator barrier. You're measuring, pre-cutting corner sections, and preparing it for attachment.

How to do it

Measure each wall: two long sides at 18 ft, two short sides at 9 ft. Mesh height needed: 3.4 ft on each side (up the wall), plus 1 to 1.3 ft extra at the bottom that folds outward as the predator apron. Pre-cut the corners according to the illustration on page 19 — cut a notch approximately 1–1.3 ft square at each bottom corner so the apron folds outward cleanly.

Do NOT cut to size yet for the greenhouse wall. Roll out the mesh for the left long wall in one piece. Once the frame is up and you can see exactly where the two poles land that define your breezeway opening, mark the gap with tape and cut the mesh to leave that ~3 ft section open.

Label each piece with painter's tape: "Front 9ft," "Back 9ft," "Right 18ft," "Left 18ft (greenhouse)."

Wear the included gloves (S). Hardware cloth edges will cut you. This is not optional. Use proper wire cutters or aviation snips — kitchen scissors will not cut hardware cloth. Cut on a flat surface.
Apron on bedrock: The manual says 1–1.3 ft apron, max 1.6 ft. On bedrock, the apron can't be buried. It will lay flat on the rock surface and be weighted down with pavers. Make the apron the full 1.3 ft for maximum predator deterrence.
Quictent Step 9 — Attach Hardware Cloth to the Frame

Manual reference: Page 20, Step 9

Parts needed: Pre-cut hardware cloth from Step 8, zip ties from N (you have 750 — use them liberally)

What you're doing and why

You're zip-tying the hardware cloth panels to the frame. The mesh wraps around the outside of the poles and gets cinched tight. This is the most time-consuming step. It's also the most important for predator protection.

How to do it

1
Start with a short end wall for practice

Start with one short end wall (front or back — NOT the one with the door). Position the mesh against the outside of the frame. The top should align with the top horizontal rail (3.4 ft up). The bottom folds outward along the ground as the apron.

2
Secure and pull taut — two-person job

Secure one side first — zip-tie the left edge to the corner upright at 6–8 inch intervals. Then pull the mesh taut and secure the opposite side. If the mesh sags, predators will push through the slack. Zip-tie along every horizontal pole the mesh crosses: 6–8 inches apart along the base (tighter = more secure), 8+ inches apart along the top and mid-height.

3
Overlap mesh sections by 8 inches minimum

Where two panels meet, zip-tie through both layers at the overlap.

4
Greenhouse (left) wall — special handling

Attach the mesh from the left corner up to the first pole marking your breezeway gap. Stop. Cut. Skip the ~3 ft breezeway opening. Resume attaching mesh from the second pole marking to the far corner. Triple the zip ties at the free edges on both sides of the gap — these are free edges that will want to curl and that a predator could peel back.

Fold the raw mesh edges back on themselves by about 1 inch and zip-tie the fold — this prevents sharp wire ends from poking out where birds could catch a foot.

5
Predator apron on bedrock

Fold the bottom 1–1.3 ft of mesh outward flat on the rock surface. Lay flat pavers or concrete blocks on the apron every 2 feet. The weight prevents predators from flipping or pushing the apron aside.

Pull it TIGHT. Sagging mesh is a failure point. Don't skimp on zip ties at the base — 6-inch spacing minimum. Trim zip tie tails after tightening — the protruding sharp tails will scratch you, catch on things, and annoy the birds.
Quictent Step 10 — Attach Chicken Wire to the Upper Walls / Gable Ends

Manual reference: Page 20, Step 10

Parts needed: Q2 (Chicken Wire roll), zip ties from N

What you're doing and why

The hardware cloth (Step 9) covers the lower ~3.4 ft of each wall. The Chicken Wire (Q2) covers the upper section — the triangular gable ends and the space between the top of the hardware cloth and the roof line. At that height, ground predators aren't the concern — it's mostly to keep the birds in.

How to do it

Unroll, measure, and cut to fit each gable and upper wall section, leaving 2–3 inches excess for overlap. Secure with zip ties at 6–8 inch spacing along the base (where it overlaps hardware cloth), 8+ inches elsewhere. Where chicken wire overlaps hardware cloth, overlap by at least 8 inches and zip-tie through both layers.

On the greenhouse wall, the chicken wire goes over the full upper section including above the breezeway gap. The breezeway is only ~3 ft tall — the space above it still needs to be enclosed. Run the chicken wire continuously across the top of that wall.
Peafowl-specific consideration: Standard chicken wire has 1-inch hex openings. Peafowl can't get through it, but a determined raccoon can tear it. If predator pressure is high in your area, consider doubling up with hardware cloth on the gable ends facing open land.
Quictent Step 11 — Install the Roof Covers

Manual reference: Page 21, Step 11

Parts needed: P (Roof Cover) ×2, O (Bungee Balls) ×24

What you're doing and why

The two Roof Covers (P) are fabric tarps that drape over the peaked roof. They provide shade (critical in Central Texas summer), rain protection, and UV barrier. Each cover spans roughly half the roof length. The Bungee Balls (O) hold the covers to the frame.

How to do it

Drape the first roof cover over the peaked roof, starting at one end. Center it so it hangs evenly on both sides. Secure with bungee balls — thread one through the grommet hole, loop around the frame pole, and hook the ball back through the loop. Repeat with the second cover on the other half. Overlap the two covers at the center by at least 6 inches.

Don't install covers in wind. They act as sails. Central Texas sun will degrade these covers — the warranty is only 180 days. Plan on replacing annually or adding a UV-resistant tarp on top.
The covers are NOT predator barriers. They're weather protection only. Your aviary netting (separate from this kit) goes over or under the covers for overhead predator protection.
Quictent Step 12 — Final Securing and Bungee Ball Check

Manual reference: Page 21, Step 12

Parts needed: Remaining bungee balls from O, screw caps from X

How to do it

1
Full perimeter walkthrough

Walk the full perimeter and check every bolted joint. Tighten any that have loosened during assembly.

2
Install screw caps

Install Screw Caps (X) on all exposed screw/bolt ends. You have 46 caps. These prevent sharp bolt ends from catching on mesh, covers, or birds.

3
Final checks

Recheck all bungee balls on the roof covers. Test the door — both latches (J) should engage cleanly. Add your secondary carabiner/slide bolt now. Check all mesh overlaps — run your hand along every seam. Lay final pavers/blocks on the predator apron.

Don't skip the screw caps. Peafowl are curious and will investigate every protruding bolt with their beaks and feet. Exposed bolt threads can injure a bird. Photograph the completed structure from all four sides before introducing birds.

TROQC Post-Assembly Checklist

These items aren't in the Quictent manual but come from your build guide and site conditions:

Item
Frame secured to 4×4 sill beams with screws at every upright (minimum)
Predator apron weighted with pavers/blocks every 2 ft around perimeter
Greenhouse-wall opening edges folded and zip-tied (no sharp wire ends)
Breezeway connection points marked with tape for Project 2
Secondary latch (carabiner or slide bolt) installed on door
Aviary netting over roof — zip-tied to every rib, 12" spacing
Nighttime flashlight walk completed — check for light gaps at base
Diagonal measurements confirmed equal (frame is square)
All zip tie tails trimmed
Door function tested with both latches
Roof covers checked for water pooling after first rain

Warranty Reference (Page 22)

The warranty warning: Modifying the structure without Quictent's written permission voids the warranty. Your breezeway opening, bedrock mounting, and latch additions are all modifications. Accept that the warranty is effectively void — you're building a peafowl fortress, not a stock chicken coop.

Ranch of Questionable Choices — Main Run Build Guide — April 2026